Our operating days for 2020:
Our diesel electric locomotive De508 will be operating on these days
January 5th and 19th & 20th (Wellington Anniversary Weekend)
February 2nd and 16th
March 1st (Childrens Day Special) and 15th
April 5th and 19th
May 3rd and 17th
From June to August we will be operating on the 1st Sunday of the Month only.
June 7th
July 5th
August 2nd
September 6th (Fathers Day Special) and 20th
October 4th and 18th

year being the most sucsessful ever. A slightly different format this year with Barlay 1749 and L4246 running in place of R.M30. This proved enormously popular and we could easily have filled 2 wagons every trip. Instead of running turn about with the regular train hauled by C847, we ran twice for each one trip of the train to cope with demand.
F139. Over the Christmas break the van was moved into the workshop for its major overhaul. The leading end bogie was removed and dismantled and it was no surprise as to the condition of the components. One wheel set has been replaced as the existing wheel had a journal that was 1/2” larger than the other, explaining why the bogie was always tilted. As this required machining to put right it was decided to fit another wheel as the flange on the existing was nearing the condemning limit. The other wheel set required the end collar built up and both wheels have been sent to Acme Engineering for machining. The elliptical springs were in better condition that the trailing bogie but have been sent for repair due to exploded rust between the leaves and broken buckles. A new set of pins and new hangers have been machined for the brake rigging and the spreaders have been built up and machined also. Both end doors and the sliding door separating the guards compartment have been removed and overhauled and are painted in primer ready for refitting. Both large sliding doors were also removed and are only fit for firewood due to rot. Thanks to the Lion foundation we have received a grant for paint for the exterior, timber to build from scratch and clad 2 side doors and hardwood for new headstocks and bogie bolsters.
should last for many years. Attention then turned to a few areas in front of the shed that required work including levelling Road 2 and repairing and packing road 4/5 turnout. Some further formation preparation earthwoarks were carried out on the extension, and the turnout purchased from KiwiRail last year and 2 sets of rails have been moved into position. Once the work required in the McKirdy yard is complete work will recommence on the much awaited project.
w over the past year is now in position on Hulls Creek Platform. Once the piling was complete the building was loaded onto a hand trolley and pushed to site and rolled off the trolley using sleepers and pieces of boiler tube. The whole operation took less than 2 hours and the results are very pleasing. With the completion of repainting the workers hut on the platform, attention is now focused on repairing and painting the jigger sheds. Now over 30 years old they are well over due for a birthday and will give a better impression as visitors ride past.